Delivery and installation

Delivery

Virtual demonstration WWTP TOPAS

Virtual demonstration
WWTP TOPAS

The WWTP TOPAS is delivered as a complete ready made wastewater treatment plant connected and tested for functionality and watertightness. It is equipped with a green colour cover with a UV filter which fits to the walls of the tank by its weight. The inside part of the cover is lined with thermal insulation which significantly restricts noise and odour escapes and, therefore, the wastewater treatment plant can be installed close to residential houses. The blower for the wastewater treatment plant is placed in a special box directly in the wastewater treatment plant, so it is not necessary to install it in the house.

Warranty

We provide a warranty period for the wastewater treatment plant for the duration of 24 months. The warranty period for the air blower is 24 months with the exception of the diaphragms in the air blower whose warranty is restricted to 12 months due to a shorter service life. The warranty period does not relate to defects caused by improper service of the wastewater treatment plant. This particularly concerns the incorrect setting of the timer and defects which can be removed according to the operation manual.

Installation

The TOPAS wastewater treatment plant is a self-supporting plastic tank which is usually installed into an excavated ditch bigger than 0.5 m (width and length) so that the cover exceeds the surface by about 0.15 m above the surrounded altered surface. By this means the wastewater treatment plant is protected against penetration of rainwater.

For the installation of the wastewater treatment plant it is recommended to use mechanization (an auto crane).

In common conditions it is sufficient to install it onto a sand bed with the thickness of 10 cm and then to backfill it with the soil from which rough stones should be removed. In the case of installation of the wastewater treatment plant into soil with a high level of underground water, we recommend to compact the bottom of the ditch with a 0.15 m wide layer of concrete or to place panels on the bottom layer. When backfilling the side walls with soil, the layer of panels should be placed on the bottom of the ditch to prevent the rising of the wastewater treatment plant.

The backfilling of the wastewater treatment plant must be performed together with the gradual filling of the wastewater treatment plant with clean water to prevent bending of walls due to the pressure from the ground.

Installation of the wastewater treatment plant
Installation of the wastewater treatment plant

Connection of the wastewater treatment plant

The wastewater treatment plant is delivered without a hole for the inflow. After installing the wastewater treatment plant the hole is to be cut at the necessary height within the size stated in the installation drawing for the respective type of wastewater treatment plant. The inflow tube must be welded to the wall of the wastewater treatment plant by a welding pistol suitable for plastic.

The wastewater treatment plant is connected to the electric distribution system (230V, 50Hz) by independent connection, ground cable CYKY 3J x 2.5 which must be installed up to the wall of the wastewater treatment plant. The electric connection and the connection in the property is not the subject of delivery of the wastewater treatment plant. The supply for the wastewater treatment plant must be protected in the electrical installation by a current protector with an actuating current of 30 mA.

Connection of the wastewater treatment plant
Connection of the wastewater treatment plant
Connection of the wastewater treatment plant
Connection of the wastewater treatment plant